Multiple-choice questions on Themes

The 7 PRINCE2® Themes - Multiple-choice questions

To conclude this section, please have a go at answering the following Foundation Examination multiple-choice questions about PRINCE® Themes. Note your answers to the following questions and then select the link to the answer page.

In the Project Management Team, which role undertakes the monitoring of all aspects of the project's performance and products?

  1. Project Board
  2. Project Assurance
  3. Project Manager
  4. Project Support

Which one of the following is an optional Plan in PRINCE2®?

  1. Team Plan
  2. Project Plan
  3. Stage Plan

Which type of control is used by the Project Board to check on progress during a Stage?

  1. Highlight Report
  2. Exception Report
  3. End Stage Assessment
  4. Exception Assessment

What is the minimum number of Stages in a PRINCE® project?

  1. Two
  2. Three
  3. Four
  4. Five

Which of the following is not a response to a threat risk?

  1. Avoid
  2. Fallback
  3. Denial

How well did you do? Here are the answers.

P3O® is a Registered Trade Mark of the Office of Government Commerce.

MSP™ is a Trade Mark of the Office of Government Commerce. The Swirl logo™ is a Trade Mark of the Office of Government Commerce.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.

M_o_R® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.