CP - Closing a Project

(Ensuring the project has done the job)

The purpose of this process is to execute a controlled close to the project, either at the planned end or premature closure.

pic_p8a.gif

The key features are to:

  1. Check the extent to which the objectives set in the PID have been met.
  2. Confirm the Customer's acceptance of the specialist products.
  3. Confirm that product maintenance arrangements are in place.
  4. Make recommendations for follow-on actions.
  5. Archive the project files.
  6. Plan a Post-Project Review or series of Reviews , if relevant.
  7. Notify relevant personnel that the project has closed.

 

 

Introduction

The 7 PRINCE2 Themes

Multiple-choice questions on Themes

The 7 PRINCE2 Processes

Multiple-choice questions on Processes

Using PRINCE2

PRINCE2® is a Registered Trade Mark of the Cabinet Office.

MSP® is a Registered Trade Mark of the Cabinet Office.

MoP™ is a Trade Mark of the Cabinet Office.

M_o_R® is a Registered Trade Mark of the Cabinet Office.

P3O® is a Registered Trade Mark of the Cabinet Office.

ITIL® and IT Infrastructure Library® are a Registered Trade Mark of the Cabinet Office.

The Swirl logo™ is a Trade Mark of the Cabinet Office.