CS - Controlling a Stage

(Daily management of the project)

After all of the initial planning has been completed and project approval obtained, this process runs continuously throughout each sequential management Stage of the project. It describes the monitoring and control functions of the Project Manager in the day-to-day management of the project.

 

Circular arrows.gif
  • Authorising work.
  • Monitoring progress.
  • Assessing issues and change requests.
  • Reporting.
  • Taking corrective action.

pic_p2b.gif

 

 

The process also covers the ongoing task of risk management, and issue and change control.

pic_p2c.gif

 

 

The Project Board meets at the end of each management Stage to review the work of the Stage just completed and to authorise the plans for the next Stage. 

 

 

Introduction

The 7 PRINCE2 Themes

Multiple-choice questions on Themes

The 7 PRINCE2 Processes

Multiple-choice questions on Processes

Using PRINCE2

PRINCE2® is a Registered Trade Mark of the Cabinet Office.

MSP® is a Registered Trade Mark of the Cabinet Office.

MoP™ is a Trade Mark of the Cabinet Office.

M_o_R® is a Registered Trade Mark of the Cabinet Office.

P3O® is a Registered Trade Mark of the Cabinet Office.

ITIL® and IT Infrastructure Library® are a Registered Trade Mark of the Cabinet Office.

The Swirl logo™ is a Trade Mark of the Cabinet Office.