DP - Directing a Project

(Taking decisions at key points)

This process runs from the start of the project until its closure. It involves the Project Board monitoring via reports, controlling through a number of decision points, and advising the Project Manager of its requirements.

  1. AUTHORISING INITIATION - Agreeing the project looks worthwhile.
  2. AUTHORISING A PROJECT - Approval of the PID and first Stage Plan.
  3. STAGE BOUNDARIES - Checking results so far to commit more resources.
  4. AD HOC DIRECTION - Providing advice and guidance.
  5. PROJECT CLOSURE - Confirming project outcome is as desired.

This process does not cover the day-to-day activities of the Project Manager.

 

 

Introduction

The 7 PRINCE2® Themes

Multiple-choice questions on Themes

The 7 PRINCE2® Processes

Multiple-choice questions on Processes

Summary

P3O® is a Registered Trade Mark of the Office of Government Commerce.

MSP™ is a Trade Mark of the Office of Government Commerce. The Swirl logo™ is a Trade Mark of the Office of Government Commerce.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.

M_o_R® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.