The 7 PRINCE2® Processes - Multiple-choice questions
To conclude this section, please have a go at answering the following Foundation Examination multiple-choice questions about PRINCE® Processes. Note your answers to the following questions and then select the link to the answer page.
During which process is the Risk Register set up?
- Planning
- Starting up a Project
- Initiating a Project
- Controlling a Stage
What is the key output from the process 'Initiating a Project'?
- Project Mandate
- Project Brief
- Project Initiation Documentation
Which process is responsible for ensuring that completed products meet their quality criteria?
- Controlling a Stage
- Managing Product Delivery
- Managing a Stage Boundary
During which process is the Next Stage Plan drafted for the Project Board's approval?
- Controlling a Stage
- Managing a Stage Boundary
- Managing Product Delivery
Which of the following is not one of the four project management strategies created in the process 'Initiating a Project'?
- Risk Management Strategy
- Quality Management Strategy
- Delivery Management Strategy
How well did you do? Here are the answers.