Multiple-choice questions on Processes

The 7 PRINCE2 Processes - Multiple-choice questions

To conclude this section, please have a go at answering the following Foundation Examination multiple-choice questions about PRINCE2 Processes. Note your answers to the following questions and then select the link to the answer page.

During which process is the Risk Register set up?

  1. Planning
  2. Starting up a Project 
  3. Initiating a Project
  4. Controlling a Stage

What is the key output from the process 'Initiating a Project'?

  1. Project Mandate
  2. Project Brief 
  3. Project Initiation Documentation

Which process is responsible for ensuring that completed products meet their quality criteria?

  1. Controlling a Stage
  2. Managing Product Delivery
  3. Managing a Stage Boundary

During which process is the Next Stage Plan drafted for the Project Board's approval?

  1. Controlling a Stage
  2. Managing a Stage Boundary
  3. Managing Product Delivery

Which of the following is not one of the four project management strategies created in the process 'Initiating a Project'?

  1. Risk Management Strategy
  2. Quality Management Strategy
  3. Delivery Management Strategy

How well did you do? Here are the answers.

PRINCE2® is a Registered Trade Mark of the Cabinet Office.

MSP® is a Registered Trade Mark of the Cabinet Office.

MoP™ is a Trade Mark of the Cabinet Office.

M_o_R® is a Registered Trade Mark of the Cabinet Office.

P3O® is a Registered Trade Mark of the Cabinet Office.

ITIL® and IT Infrastructure Library® are a Registered Trade Mark of the Cabinet Office.

The Swirl logo™ is a Trade Mark of the Cabinet Office.