Project Mandate
Appoint the Executive and the Project Manager
Capture previous lessons
Prepare the outline Business Case
Design and appoint the project management team
Select the project approach and assemble the Project Brief
Plan the initiation stage
Conclusion
Glossary
Project Mandate

The originator or sponsor of a project will produce a Project Mandate containing all or some of the following basic information:

 

  • Background to the project - Where did the idea come from?

pic_s1a.gif

  • Project objectives - What is the desired outcome?
  • Scope of the project - What is included (and what is not)?
  • Customer's quality expectations - Of the product or deliverable.
  • Outline business case - Justification and expected benefits.
  • Potential project management team-members - People playing which roles?
  • Any constraints or interfaces - Financial limits or existing systems?

pic_s1b.gif

 

 

Project MandateAppoint the Executive and the Project ManagerCapture previous lessonsDesign and appoint the project management team
Prepare the outline Business CaseSelect the project approach and assemble the Project BriefPlan the initiation stageConclusion

P3O® is a Registered Trade Mark of the Office of Government Commerce.

MSP™ is a Trade Mark of the Office of Government Commerce. The Swirl logo™ is a Trade Mark of the Office of Government Commerce.

PRINCE2® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.

M_o_R® is a Registered Trade Mark of the Office of Government Commerce in the United Kingdom and other countries.